Mirada Bridge El Nino Bluff Protection is Temporarily Suspended Until Week of November 23rd, 2026 as Sandbag Manufacturer Procures Additional Material

Getting your Trinity Audio player ready...

UPDATE. From San Mateo County Public Works “Emergency Mirada Road Bridge Temporary Bluff Protection Project Update” webpage on November 13th, 2026.

About the Project
The County of San Mateo Department of Public Works has contracted with Andreini Bros, Inc. to complete the Emergency Mirada Road Bridge Temporary Bluff Protection Project (Project), in the community of Miramar, near Half Moon Bay, in San Mateo County. This project is to protect the exposed bluff face and seawall in anticipation of a stronger than usual storm season this upcoming winter due to El Niño conditions. Flexible Intermediate Bulk Containers (FIBCs’ or large sandbags) will be installed on the beach to provide a barrier and dissipate the wave energy as it reaches the bluff.

Work Schedule
Construction work began on November 3, 2026 and will typically occur Monday through Friday, from 8:00 a.m. to 5:00 p.m.  Work is anticipated to be completed by December 2026.

UPDATE as of November 13, 2026
FIBC placement is temporarily on pause while the manufacturer procures additional material. Work is expected to resume the week of November 23rd, 2026.

Mirada Bridge Impact
The Mirada pedestrian bridge will remain accessible during construction. Pedestrians and cyclists may experience a brief (about 15 minutes) delay due to construction operations. Flaggers will be on site to guide pedestrians and cyclists safely through the work zone. 

The County and contractor will make every effort to maintain pedestrian access through or around the work area, based on construction operations, available space, and public safety conditions.


Traffic and Parking Impacts
Parking in the work area will also be restricted during work hours. Please adhere to all posted “No Parking” signs. Personal vehicles should be moved out of the area prior to 8am on workdays.

Beach Access
The beach will generally remain open during work; however, portions of the beach will be blocked off for public safety.

Project Updates During Construction
For weekly project updates, including construction progress, anticipated work activities, and any pedestrian, road, bridge, parking, or beach-access limitations for the following week, please visit the project website: https://www.smcgov.org/publicworks/mirada-bluff-protection

If you have questions about the project not answered here, we recommend contacting us at following address: miradaroadrepair@smcgov.org

Thank you for your patience and cooperation as we complete this work. 


More on the Mirada Bridge on Coastside Buzz




San Mateo County Board of Supervisors (BoS) Agendas

The Supervisors meet on the 2nd and 4th Tuesdays of the month at 9:00am, as a hybrid meeting.

mdrag
Author: mdrag

x

Leave a Reply

Your email address will not be published. Required fields are marked *