San Mateo Supervisors Approve $4M for Construction of the Multimodal Trail Segment 1: Mirada North to Coronado

Getting your Trinity Audio player ready...

STAFF REPORT. From the San Mateo County Supervisors Agenda for meeting held on Tuesday, March 8th, 2022 at 9:00am by Zoom.

 

Adopt a resolution:

A) Adopting plans and specifications, including conformance with prevailing wage scale requirements, for the Midcoast Multi-Modal Trail Improvements Project; and

B) Authorizing the President of the Board to execute an agreement with Minerva Construction, Inc., in the amount of $3,483,652 for the Midcoast Multi-Modal Trail Improvements Project; and

C) Authorizing the Director of Public Works to: 1. Execute subsequent change orders to grant time extensions for project completion and payment up to a maximum aggregate amount not to exceed $348,365.20, or approximately ten percent of the agreement amount; and 2. Approve payment up to the not to exceed amount of $3,832,017.20 for items requiring adjustment based on unit bid prices without execution of a change order.

 

To: Honorable Board of Supervisors

From:  Ann M. Stillman, Interim Director, Department of Public Works

Subject:  Midcoast Multi-Modal Trail Improvements Project

[County Project No. P29F1; Project File No. E4952]

 

 

RECOMMENDATION:

Adopt a resolution:

 

A)  Adopting plans and specifications, including conformance with prevailing wage scale requirements, for the Midcoast Multi-Modal Trail Improvements Project; and

 

B)  Authorizing the President of the Board to execute an agreement with Minerva Construction, Inc., in the amount of $3,483,652 for the Midcoast Multi-Modal Trail Improvements Project; and

 

C)  Authorizing the Director of Public Works to:

 

1. Execute subsequent change orders to grant time extensions for project completion and payment up to a maximum aggregate amount not to exceed $348,365.20, or approximately ten percent of the agreement amount; and

 

2. Approve payment up to the not to exceed amount of $3,832,017.20 for items requiring adjustment based on unit bid prices without execution of a change order.

 

 

BACKGROUND:

On March 23, 2021, this Board adopted Resolution No. 078090, which authorized the Director of Public Works to proceed with finalizing the plans and specifications for the Midcoast Multi-Modal Trail Improvements Project (Project) and authorized the Director of Public Works to proceed with advertising for bids on the Project and reporting back to this Board with recommendations on awarding a contract.

 

On May 4, 2021, this Board adopted Resolution No. 078161, which authorized the County Manager or designee to execute a Maintenance Agreement between the County of San Mateo and the California Department of Transportation (Caltrans) for the Project (Maintenance Agreement) upon Caltrans’ legal certification of the Maintenance Agreement.

 

DISCUSSION:

The Department has finalized the plans and specifications and advertised the Project for bid. The County has executed the Maintenance Agreement and obtained an encroachment permit from Caltrans for the Project since the work is in the Caltrans Highway 1 right-of-way.

 

On Wednesday, February 23, 2022, at 2:30pm, bids were accepted for this Project and subsequently referred to the Department for checking and recommendation. The bid of:

 

Minerva Construction, Inc.

1485 Bayshore Blvd, Suite 210

San Francisco, CA 94124

 

at $3,483,652 was the lowest responsible bid received for the work. The Engineer’s Estimate was $3,332,000. A summary of the bids received is attached as Exhibit “A”.

 

County Counsel has reviewed and approved the resolution and agreement as to form.

 

FISCAL IMPACT:

The total estimated cost for construction is $3,832,017.20, which includes authorization for up to $348,365.20 in change orders as the work is bid on a unit price basis. The contingency is used to pay the contractor for any unforeseen conditions not anticipated in the construction agreement documents.

 

The Project has been budgeted and will be financed as follows:

 

Measure K                                                                              $1,199,580.00

General Fund (Parks and Marina Projects)                     $2,632,437.20

Total Cost                                                                                 $3,832,017.20

 


 

 

Midcoast Multimodal Trail Project

From San Mateo County website.

 

 


More on the Multimodal Trail on Coastside Buzz

 

CUSD Donates Land Speeding Construction of Multi-Modal Trail For This Summer Making E.G. Elementary Access Safer

February 16th, 2022

Hwy 1 West Side Parallel Walking and Biking Trail Grant Application for Construction Phase

July 8th, 2019

 


 

San Mateo County Supervisors

2022 BOARD OF SUPERVISORS

 

Supervisor Dave Pine for District 1

DISTRICT 1

Dave Pine

Vice President

Supervisor Carole Groom for District 2

DISTRICT 2

Carole Groom

Supervisor Don Horsley for District 3

DISTRICT 3

Don Horsley

President

Supervisor Warren Slocum for District 4

DISTRICT 4

Warren Slocum

 

Supervisor David Canepa for District 5

DISTRICT 5

David Canepa

Coastside Buzz
Author: Coastside Buzz

Me