Project Status
Bridge Closure:
- Bridge was closed on July 27, 2020 due to the severe rusting and poor condition of the bridge (see Bridge Closure Announcement).
- The detour route is opened on September 21, 2020 after Public Works obtained Caltran’s approval to provide a detour route on HWY 1 shoulder within their right of way.
Construction:
- Anticipated construction: June 2022
- 120 working days (bridge fabrication may extend construction window)
Public Works Contact
Website Updated as of May 9, 2022
Good Bye Detour! Medio/Miramar Bridge Construction Starts June 2020; Open by December 2022
VIDEO. From the Half Moon Bay Bicycle Pedestrian Advisory Committee (BPAC) meeting on Thursday, May 5th, 2022 at 6:30pm by Zoom.
HMB Senior Engineer, Maz Bozorginia, reports back on the contractor pre-construction meeting on May 3rd, 2022.
County has contractor and notice to proceed is 5/23/22.
Construction start date is June, 120 days of work, open by before Thanksgiving, December 2022; supply chain issues not withstanding.
The Full History ~ Most Recent First
San Mateo County Supervisors Award $4M for the Summer 2022 Re-Construction of the Medio Creek/Miramar Bridge and Bank Stabilization
Medio Creek/Miramar Bridge 3/2022 Report: San Mateo County Funds Design Update After Buttress Falls During Storms
Arroyo de Medio Bridge Butresses Crumbles After 6″ of Rain Falls on the Coastside
Medio-Miramar Bridge Hwy 1 Detour Barrier Hit By Vehicle Over Memorial Weekend Making Detour Even More Dangerous
California Coastal Commission Unanimously Approves the Replacement of Medio/Miramar Bridge
California Coastal Commission Staff Recommends Medio/Miramar Bridge Repair with Minimized Rip-Rap
Granada Community Services District (GCSD) Moves Forward on Medio Bridge Sewer Pipe Replacement
If CCC Approved Point Arena Armoring In 2021, Will They Approve Medio Bridge Armoring in Miramar?
Miramar Residents Collect 1,128 Signatures For Petition to “Replace the Medio Creek Bridge At Current Location”
Miramar Residents Want the Medio/Miramar Bridge Replaced in 2021
MCC Discussion: Miramar Bridge Retreat to Alameda Blvd or Buy the Old Miramar Train Depot Vacant Lot?
5 Route Alternatives for the Mirada/ Miramar Road Bridge Fix ~ Public Comment Period Ends Jan. 15th, 2021
Miramar Bridge Hwy 1 Detour CalTrans Final Striping 1-Day Work
Miramar Bridge Hwy 1 Detour Construction Begins Friday 9/18/2020
Hwy 1 Detour Discussion for the Miramar Bridge Closure at the MCC Meeting
CRACKS! Check Out the CLOSED Miramar/Medio Bridge Foundation
Miramar Bicycle and Pedestrian Bridge Closed to Prepare for New Bridge
This bridge closed July 2020, two FULL years ago. Disgraceful that work STILL not completed!
I had no idea the extent that the concrete arch under the Medio Creek bridge had deteriorated! I see why they closed the bridge!