VIDEO and STAFF REPORT. From the San Mateo County Harbor District Commissioner’s meeting on Wednesday, July 17th, 2024 at 10:00am as a hybrid meeting. Comments in person or by email only.
Harbor District Chair, Tom Mattusch, introduces General Manager Jim Pruett.
Full Staff Report
SUBJECT: Surfers Beach Replenishment Pilot Project Update and Consultant Damitz Continued D&E Proposal Consideration.
Recommendation/Motion: Motion: Approve a proposal from consultant Brad Damitz for an amount not to exceed $38,400 to complete the planning and permitting phase project management for the Surfers Beach Restoration Pilot Project and the Pillar Point Harbor-Wide Eelgrass Mitigation Program through completion of the bid process and contract approval for construction, and approve an increase in Capital Expenditure Appropriations of this amount to be funded by available working capital.
Construction for the Surfers Beach Project is being planned for a spring/summer 2025 timeframe. Permits have been approved by:
- California Coastal Commission
- SF Regional Water Quality Control Board
- Army Corps of Engineers
- Caltrans
- The last remaining permit from Monterey Bay National Marine Sanctuaries was executed July 11, 2024, so all permits have finally been approved
>>> READ MORE
Permit Confirmation from the Monterey Bay National Marine Sanctuaries
From: UNITED STATES DEPARTMENT OF COMMERCE National Oceanic and Atmospheric Administration NATIONAL OCEAN SERVICE and Greater Farallones and Cordell Bank National Marine Sanctuaries
Dear Mr. Pruett:
The National Oceanic and Atmospheric Administration, Office of National Marine Sanctuaries (ONMS) has approved the issuance of permit number MBNMS-2022-021 to conduct activities within Monterey Bay National Marine Sanctuary (sanctuary) for management purposes. Activities are to be conducted in accordance with the permit application and all supporting materials submitted to the sanctuary, and the terms and conditions of permit number MBNMS-2022-021 (enclosed).
>>> READ MORE
Dredge needed for sand replenishment at Surfers Beach
Harbor District: Pillar Point Harbor – East Outer Harbor Dredge Project to Include Surfers Beach Replenishment and Eelgrass Mitigation Plan
More on Pillar Point Dredge and Surfers Beach Sand Replenishment Pilot on Coastside Buzz
Artificial Reefs (and Dredging) as a Solution on Coastside Buzz
Surfers’ Beach Pilot Restoration Project (Harbor District) on the MCC
More on the Harbor District on Coastside Buzz
San Mateo County Harbor District Board Meetings ~ 3rd Wednesday @ 10:00am
Watch remotely. Comments and questions by email.
Harbor District Agendas and Remote Meeting Links
2023 Board of Harbor Commissioners Contact Information:
Please note that email correspondence sent to or from Members of the Harbor Commission via the District’s website are considered public records and may be subject to disclosure and additional distribution pursuant to the Public Records Act and the Brown Act.
To email the entire Harbor Commission, click here.
Commissioner Tom Mattusch
DISTRICT 4
Commissioner Kathryn Slater-Carter
DISTRICT 3
Commissioner George Domurat
DISTRICT 2
Commissioner Virginia Chang Kiraly
DISTRICT 5
Commissioner William Zemke
DISTRICT 1