Good Bye Detour! Medio/Miramar Bridge Construction Starts June 2020; Open by December 2022

Getting your Trinity Audio player ready...

VIDEO. From the Half Moon Bay Bicycle Pedestrian Advisory Committee (BPAC) meeting on Thursday, May 5th, 2022 at 6:30pm by Zoom.

HMB Senior Engineer, Maz Bozorginia, reports back on the contractor pre-construction meeting on May 3rd, 2022.

County has contractor and notice to proceed is 5/23/22.

Construction start date is June, 120 days of work, open by before Thanksgiving, December 2022; supply chain issues not withstanding.

 

 


The Full History ~ Most Recent First

 

San Mateo County Supervisors Award $4M for the Summer 2022 Re-Construction of the Medio Creek/Miramar Bridge and Bank Stabilization

 

Medio Creek/Miramar Bridge 3/2022 Report: San Mateo County Funds Design Update After Buttress Falls During Storms

 

Arroyo de Medio Bridge Butresses Crumbles After 6″ of Rain Falls on the Coastside

 

Medio-Miramar Bridge Hwy 1 Detour Barrier Hit By Vehicle Over Memorial Weekend Making Detour Even More Dangerous

 

California Coastal Commission Unanimously Approves the Replacement of Medio/Miramar Bridge

 

California Coastal Commission Staff Recommends Medio/Miramar Bridge Repair with Minimized Rip-Rap

 

Granada Community Services District (GCSD) Moves Forward on Medio Bridge Sewer Pipe Replacement

 

If CCC Approved Point Arena Armoring In 2021, Will They Approve Medio Bridge Armoring in Miramar?

 

Miramar Residents Collect 1,128 Signatures For Petition to “Replace the Medio Creek Bridge At Current Location”

 

Miramar Residents Want the Medio/Miramar Bridge Replaced in 2021

 

MCC Discussion: Miramar Bridge Retreat to Alameda Blvd or Buy the Old Miramar Train Depot Vacant Lot?

 

5 Route Alternatives for the Mirada/ Miramar Road Bridge Fix ~ Public Comment Period Ends Jan. 15th, 2021

 

Miramar Bridge Hwy 1 Detour CalTrans Final Striping 1-Day Work

 

Miramar Bridge Hwy 1 Detour Construction Begins Friday 9/18/2020

 

Hwy 1 Detour Discussion for the Miramar Bridge Closure at the MCC Meeting

 

CRACKS! Check Out the CLOSED Miramar/Medio Bridge Foundation

 

Miramar Bicycle and Pedestrian Bridge Closed to Prepare for New Bridge

 

Coastside Buzz
Author: Coastside Buzz

Me

One thought on “Good Bye Detour! Medio/Miramar Bridge Construction Starts June 2020; Open by December 2022

Comments are closed.